Arden’s East Tower is really starting to take shape. Drywall is now completed with interior painting soon to be finished. Kitchen and bathroom cabinets have been installed up to the 15th floor with appliances installed up to the 11th floor. The West Tower continues to make great progress as well with window installation recently completed, drywall installed up to the 11th floor and tile, hardwood flooring, cabinets and appliances completed up to the 5th floor.